Introduction
Liquidated damages clauses are common in oil and gas contracts. They appear in Engineering Procurement and Construction (EPC) contracts, fabrication agreements, drilling contracts, construction projects and long-term services arrangements. Their purpose is simple. The parties agree in advance what will happen if a particular obligation is not met.
In practice, however, liquidated damages provisions often give rise to disputes. Are they a genuine estimate of loss or merely a penalty? Must actual loss be proven? Do they limit liability or simply provide an additional remedy? Can a party recover liquidated damages and still claim further damages?
These questions are particularly important in the oil and gas industry where delays, missed milestones and performance shortfalls can have significant commercial consequences.
The Malaysian Position
Liquidated damages in Malaysia are governed primarily by section 75 of the Contracts Act 1950. The section provides that where a contract specifies an amount payable upon breach, the innocent party is entitled to reasonable compensation not exceeding the amount stated in the contract.
The law was clarified by the Federal Court in Cubic Electronics Sdn Bhd (in liquidation) v Mars Telecommunications Sdn Bhd. The Court confirmed that a claimant is not required to prove its actual loss in every case before recovering liquidated damages. Instead, the court must determine what constitutes reasonable compensation, taking into account the circumstances of the case and the parties’ legitimate interests.
As a result, simply describing a clause as a “genuine pre-estimate of loss” or stating that it is “not a penalty” does not automatically make it enforceable. The court will still consider whether the amount claimed represents reasonable compensation.
Why Liquidated Damages Are Common in Oil and Gas Contracts
Liquidated damages are particularly prevalent in the oil and gas industry because the consequences of delay are often significant, difficult to quantify precisely and capable of cascading across an entire project.
In many industries, a delay may result in little more than inconvenience or modest financial loss. In the oil and gas sector, however, a delayed offshore platform, pipeline, processing facility, FPSO, refinery unit or production enhancement project can postpone the commencement of hydrocarbon production. The resulting loss of revenue may amount to hundreds of thousands, and in some projects, millions of dollars per day.
Against that backdrop, it would be commercially unrealistic for operators to leave such risks entirely unaddressed. Equally, it would be commercially unsustainable for contractors to assume unlimited exposure to the operator’s actual losses. A fabrication contractor, vessel operator, engineering consultant or specialist subcontractor may have contract values that are entirely disproportionate to the potential revenue losses suffered by an oil field operator. If every delay exposed the contractor to uncapped claims based on actual production losses, many contractors would simply be unwilling or financially unable to undertake the work.
Liquidated damages therefore serve an important risk allocation function. They allow the parties to agree in advance on the financial consequences of specific delays or performance failures, creating certainty for both sides. The operator obtains a predictable remedy without having to prove every aspect of its loss, while the contractor gains visibility over its potential exposure and can price that risk into its tender.
In that sense, liquidated damages are not merely a compensation mechanism. They also protect the wider project ecosystem. Major oil and gas developments typically involve numerous contractors, subcontractors, suppliers, financiers and insurers. The viability of that ecosystem depends on risks being allocated in a manner that is commercially manageable. An agreed liquidated damages regime enables contractors to participate in projects without assuming catastrophic liability that could threaten their financial viability, while still incentivising timely and compliant performance.
Sword or Shield?
Liquidated damages can operate as both.
For the project owner or employer, liquidated damages provide a ready mechanism for recovery. Instead of undertaking a lengthy exercise to quantify every item of loss, the contract already contains a formula for compensation.
For the contractor, the same clause may provide certainty. The contractor knows the financial consequences of a particular failure and can price that risk into its tender.
Do Liquidated Damages Limit Liability?
One of the most common misunderstandings is that every liquidated damages clause automatically limits liability.
That is not necessarily correct.
The Federal Court in Cubic Electronics recognised that the stipulated sum may operate as a cap for the particular breach to which the liquidated damages clause applies.
However, this does not mean that the clause automatically becomes a general limitation of liability provision covering all obligations under the contract.
A delay liquidated damages clause may govern delay. It does not necessarily govern defects, property damage, pollution liabilities, intellectual property claims, confidentiality breaches or indemnity obligations. Those issues depend on the wording of the contract as a whole.
Accordingly, parties should avoid assuming that a liquidated damages cap and an overall liability cap are the same thing.
Must Actual Loss Be Proven?
Following Cubic Electronics, the answer is generally no.
The innocent party must still establish the breach and show that the liquidated damages provision has been triggered. However, it is no longer necessary in every case to produce evidence proving actual loss dollar for dollar before compensation can be awarded.
That does not mean evidence of loss has become irrelevant. Evidence may still assist the court in determining whether the stipulated amount represents reasonable compensation and whether it is proportionate to the legitimate interests that the clause seeks to protect.
Are Liquidated Damages the Sole and Exclusive Remedy?
The answer depends on the wording of the contract.
Some contracts expressly state that liquidated damages are the sole and exclusive remedy for a specified breach. Such wording generally provides certainty because it demonstrates that the parties intended the liquidated damages regime to replace other monetary claims arising from that particular default.
Other contracts preserve all rights and remedies available under the contract.
The difficulty arises when parties attempt to recover liquidated damages and additional damages arising from the same breach.
The recent Court of Appeal decision in Savelite Engineering Sdn Bhd v Askey Media Technology Sdn Bhd and another appeal [2025] MLJU 2258 is particularly significant. The Court held that where liquidated damages had already been prescribed for the delay, the employer was not permitted to recover additional losses arising from the same delay beyond the amount allowed under the liquidated damages regime.
The decision reinforces an important principle. A party should not obtain double recovery for the same breach merely by relying on broad reservation of rights language.
What Does “Without Prejudice to Other Rights” Actually Mean?
Oil and gas contracts frequently state that liquidated damages are payable without prejudice to other rights and remedies.
In many cases, this wording is intended to preserve rights such as termination, continued performance obligations, recourse to performance security, set-off rights and claims arising from separate breaches of contract.
It should not automatically be interpreted as allowing recovery of liquidated damages together with further general damages for exactly the same breach.
Whether additional claims remain available depends on the language of the contract and whether the additional remedy addresses a separate loss or obligation.
Time Is Still Important
Many oil and gas contracts expressly state that time is of the essence.
This wording can have significant consequences. Depending on the circumstances, a serious delay may entitle the innocent party not only to liquidated damages but also to exercise contractual rights such as termination.
However, whether termination remains available will often depend on subsequent conduct, election and the terms of the contract itself.
Practical Drafting Lessons
From a risk management perspective, parties should clearly identify:
• Which obligations are subject to liquidated damages.
• Whether liquidated damages are delay damages, performance damages or both.
• Whether liquidated damages are intended to be the sole remedy for the specified breach.
• Whether other claims survive alongside the liquidated damages regime.
• How liquidated damages interact with limitation of liability provisions.
• Whether guarantees, retention monies and performance bonds can be used to satisfy liquidated damages claims.
The clearer the drafting, the lower the likelihood of costly disputes when a project encounters difficulties.
Conclusion
Liquidated damages occupy a unique position in Malaysian law. They provide certainty for project owners while also giving contractors a degree of predictability regarding their exposure.
After Cubic Electronics, the focus is no longer on whether a clause is labelled as a penalty or a genuine pre-estimate of loss. The central question is whether the amount claimed represents reasonable compensation within the meaning of section 75 of the Contracts Act 1950.
For companies operating in the oil and gas sector, careful drafting remains essential. The wording of the liquidated damages clause, its interaction with liability caps, indemnities, guarantees and termination rights, and whether it is intended to be an exclusive remedy may ultimately determine the outcome of a dispute.
